Project Portfolio - Office Buildings
Project Portfolio Overview
Parking Structures
Hotels

Educational - Concrete

Wood Framing
Residential
Office Buildings
Correction Facilities
Medical Facilities
Convention & Sporting Complexes
Manufacturing Structures
Seismic Upgrade / Retrofit
Public Municipal Facilities
Civil and Site Work Projects
Utility / Labs / Special Condition
Concrete Packages
Design Build Parking Structures
Complete List of All Projects
Statistics:
Suspended Slab 680,000 sf.
Columns 2,342 ea.
Shear, Stair & Elevator Walls 236,000 csf.
Client:
Nordic / PCL Joint Venture
MCC Project Manager:
Chris Moes
MCC Project Engineer:
Chris Moes, Ben Sugiyama
MCC Superintendent:
Chris Moes, Ben Sugiyama
 Office Buildings / Structural Frames
Example: Job # 383 - Gap World Headquarters, San Francisco, CA
Project Photos Details
Project Description:
The GAP Headquarters building is comprised of 160,000 square feet of below grade parking and 19 levels of office space above grade. The perimeter walls of the basement area is constructed of shotcrete against a steel pile-wood lagging retention system.

Portions of the foundation are below the water level of the San Francisco Bay directly across the embarcadero from the project site. The foundations were saw cut through a rat slab, dug neat and a temporary retention system was installed to hold back the differing soils encountered during structural the excavation. During structural excavation numerous old wood piers were encounter, which were either removed or cut off to facilitate the foundation system.

The lower parking garage levels consisted of perimeter shotcrete walls, interior columns and shear walls supporting an 8” to 10” thick suspended slab with capitals.

The major portion of the project was the cast-in-place elevator core which started from a large mat foundation in the center of the site. Due to schedule and hoisting constraints it was necessary to form the core utilizing a self-climbing wall forming system. The system that was used for this project was designed using steel form panels attached to a self-climbing electric screw jacking system. This method allowed the entire forming system to be raised at one time without the use of the project tower crane.

The 10” structural slabs in between the core walls were delayed and cast later to minimize their impact on the critical path schedule items.

In addition to the core walls and basement areas, numerous planter walls and curbs were constructed throughout the project.

To combine the structural concrete core with the structural steel elements it was necessary to install numerous steel embeds to facilitate the connection between the two systems.